AIA-MBA Home Page
Organization
Drawings and Specifications
Bidding
Contracts
Temporary Services
Bonds, Insurance, & Liability
Safety Responsibilities
Release of Liens
Supplements
Contact

Contracts


Section D-1
Changes in the Work

Whenever a change in the work is required, the Joint Committee recommends that an adjustment in the contract sum be made on a lump sum basis.  The amount for such changes is to be submitted by the contractor, and agreed to by the Architect and Owner, with a formal change order issued, before the work is commenced.

When a lump sum agreement is not practical, the changes may be performed on a cost-plus basis, with a reasonable allowance for overhead and profit, or an agreed-upon unit price basis in accordance with the requirement of the General Conditions of the Contract.

A change in the work may also require a change in the contract time.  Time extension should be agreed upon at the same time as the change in the contract sum.  All parties involved in the project, including all subcontractors, should be allowed to evaluate changes and be notified of all agreed-upon changes and/or time extensions.

 

Revised October 2009
Revised January 1990
Reviewed April 1987
Revised December 1981
Revised September 1981
Reviewed April 1976
Revised November 1971
Revised January 1967

Approved September 1958


Top of Page | AIA-MBA Home Page | Organization | Drawings & Specifications | Bidding | Contracts | Temporary Services | Bonds, Insurance & Liability | Safety Responsibilities | Release of Liens | Procurement Methods & Supplements | Contact Us