











|

D-2,
April, 1987
Final
Acceptance of Contract Work
It is recommended that the following procedures be
observed:
- As the work nears completion, the Contractor
shall review the requirements of the Contract
Documents, shall inspect the work, and shall
inform all parties involved of work to be
corrected or completed deeming the project
substantially complete.
- Upon receipt of a written statement from the
Contractor signifying that work is substantially
complete and containing the list of items to be
corrected or completed, the Architect will visit
the site to verify. If the Architect agrees that
the work is substantially complete in accordance
with the Contract Documents, he will make a
pre-final inspection in the presence of a
representative of the Contractor and will prepare
a "Certificate of Substantial
Completion".
- The Architect will confirm the list of required
corrections and attach the punch list to the
Certificate of Substantial Completion. The
Contractor shall divide the list into each trade,
with provision on the list for indicating
satisfactory completion by checking or punching.
When the Contractor has satisfied himself that
all items on the list have been satisfactorily
corrected or completed, the Contractor shall
notify the Architect in writing and make
Application for Final Payment.
- The Architect will make the final inspection to
confirm the Contractor's statement and, based
upon the condition of work inspected, the
Architect will take appropriate action.
- Punch list work should not delay normal issuance
of Architect's Certificates, including
Certificates for reduction and/or elimination of
retained percentage due the Contractor, provided
a sum sufficient to complete remaining work is
withheld.
- 6. Since it is the Contractor's judgment as to
when to notify the Architect of "Substantial
Completion", and to minimize the list of
items to be completed, the "Substantial
Completion" should be established as the
date the Owner can occupy and utilize the work or
a designated portion for its intended use.
- The Architect/Engineer shares a responsibility to
make the Contractor aware, throughout the course
of the work, of conditions known to him that
would eventually become punch list items if not
promptly corrected, thus minimizing corrective
work and reducing the number of final punch list
items.
- It is also the intention of this recommendation
that, whenever possible, there should be only one
complete punch list developed and that the items
on the list should be corrected or completed by
the Contractor within a reasonable and stipulated
number of days after issuance.
- When the Contract Documents are satisfied and the
punch list is completed, the Architect will
promptly issue a final Certificate for Payment
representing his acceptance of the work.
Revised April 1987
Reviewed January 1987
Approved April 1976
Top of Page | AIA-MBA
Home Page | Organization | Drawings
& Specifications | Bidding | Contracts | Temporary
Services | Bonds, Insurance &
Liability | Safety Responsibilities | Release
of Liens | Procurement Methods
& Supplements | Contact Us
|