
Section F-1
Bid Guarantee
When a Bid Guarantee is required, the Joint Committee
recommends the following:
1. The Bid Guarantee should be in the form of a Bid
Bond, certified check, or bank cashier's check. A
specific amount should be noted for the bid guarantee
rather than a percentage of the bid amount, and this
guarantee should not exceed ten percent (10%) of the
estimated amount of the base bid.
2. All bid guarantees not forfeited under the terms of
the bidding, except for the two lowest responsible
bidders, should be returned on or before the sixth day
subsequent to the bid opening. If the contract is not
awarded, the bid guarantees of the two lowest responsible
bidders should be returned within forty-five (45) days
subsequent to the bid opening, unless an extension is
granted by those bidders.
3. It is recommended that bid bonds be provided as bid
guarantees, but the bidder shall have the option of
furnishing a check as noted above. If checks are
mandatory as bid guarantees, and the contract bond is not
executed within ten (10) days subsequent to the bid
opening, the retained checks shall be exchanged for bid
bonds at the option of the bidders.
4. If a bid bond is furnished, it should include a
statement to the effect that if the Contractor is awarded
the contract, the Surety Company will also provide the
Contract Bonds required under the contract.
5. The name of the a specific Surety Company should
not be specified in the requirements, nor should the
Owner be permitted to require that only one Surety
Company be allowed to supply the bonds.
6. Standard AIA contract documents should be used
wherever possible.
Reviewed March 2011
Reviewed July 2010
Revised May 1987
Reviewed April 1986
Reviewed June 1977
Revised November 1971
Approved March, 1968
Top of Page | AIA-MBA
Home Page | Organization | Drawings
& Specifications | Bidding | Contracts | Temporary
Services | Bonds, Insurance &
Liability | Safety Responsibilities | Release
of Liens | Procurement Methods
& Supplements | Contact Us |