











|
Section C-5
Bidding on Unclassified Excavation
The Joint Committee recommends that Contract Documents allow Contractors
the means to be fairly compensated for Work, and to that end, favors
classifying types of excavation.
COMMENTARY: The Joint Committee believes that the
purpose of the bidding process is to provide a means by which the Owner
can obtain comparative pricing of like products. In the ideal world,
the process produces a win-win relationship between the Owner and Contractor.
Excavation work has been specified as either classified or unclassified.
Unclassified excavation makes no distinction between the requirements
to remove loose fill at one extreme to rock at the other extreme. The
Bidder, by accepting the conditions of unclassified excavation, assumes
the risk for whatever appears. Because it is impossible, even with an
investigation of the subsurface conditions, to know with absolute certainty
what will be encountered during excavation, it is highly likely that
someone loses.
Excavation should be classified with a description of material and
a definition of the effort required for removal. It is recommended that
specific language be incorporated into the specifications to quantify
the anticipated type of excavation to be included in the base bid and
clearly define rock excavation. An example of such language is:
-
Work, in general, consists of, but is not necessarily limited
to:
a. Bulk excavation for building pad and foundations, parking lots,
access roads, sidewalks and other structures and site improvements
as indicated on the Drawings.
b. Trench excavation, backfilling, compaction, thrust blocks, and
related items to complete installation of sanitary and storm sewers,
natural gas piping, underground electrical service, water service,
and other site utilities as indicated on the Drawings.
i. All excavation shall be assumed to be earth (non-rock).
ii. Bidder shall provide a unit price for rock excavation as an
extra to the Contract.
iii. Bidder shall provide a unit price for off-site disposal of
unsuitable material and replacement with suitable backfill material
compacted in place as an extra to the Contract.
- Earth excavation includes excavation of pavements and other obstructions
visible on surface; underground structures, utilities, and other items
indicated to be demolished and
- removed; together with earth and other materials encountered that
are not classified as rock or unauthorized excavation.
- Rock Excavation:
a. When rock is encountered within the limits of the excavation, immediately
notify the Owner and Architect and do not proceed further until instructions
are received and measurements made for the purpose of establishing
the and volume of rock excavation.
b. Volume of rock excavation shall be determined by the location of
the “pay lines”. Pay lines shall be determined with the
Owner and Architect prior to commencement of rock excavation and shall
be the basis for payment. Pay lines shall be defined as:
i. The elevation of the bottom of the foundation of the structure
or the designated over-excavation below pipes, conduits, floor slabs,
foundations, site amenities, etc.
ii. The vertical side planes which will afford an adequate and safe
working area between the structure wall and face of the cut.
c. Rock excavation consists of the removal of hard igneous, metamorphic,
and/or sedimentary rock which cannot be excavated without blasting
or by means of a track mounted power excavator, equivalent to Caterpillar
Model No. 215C LC, and rated at not less than 115 HP flywheel power
and 32,000 pound drawbar pull and equipped with a short stick and
a 42 inch wide, short tip radius rock bucket rated at 0.81 cubic yard
(heaped) capacity, and all boulders or other detached stones each
having a volume of ½ cubic yard or more. Trenches in excess
of 10 feet in width and pits in excess of 30 feet in either length
or width are classified as open excavation.
d. Unit Prices, measured in place, shall be provided for:
i. Mass cut, spoiled – over 7’-0” wide, fractured
by blasting or machine, loaded, removed, and disposed of on-site.
ii. Mass cut, hauled – over 7’-0” wide, fractured
by blasting or machine, loaded, removed, and disposed of off-site.
iii. Trench cut, spoiled – under 7’-0” wide, fractured
by blasting or machine, loaded, removed, and disposed of on-site.
iv. Trench cut, hauled – under 7’-0” wide, fractured
by blasting or machine, loaded, removed, and disposed of off-site.
v. Hand removal, spoiled – rock fractured by hand tools (i.e.
pneumatic) loaded, removed, and disposed of on-site.
vi. Hand removal, hauled – rock fractured by hand tools (i.e.
pneumatic) loaded, removed, and disposed of off-site.
e. Unit prices shall be used to calculate the net change to the contract
amount by means of multiplying the volume of rock excavation determined
under Section 2.b by the Unit Price determined under Section 2.g less
the value of earth excavation for this volume already included in
the contract.
- Unsuitable Material:
a. Materials unsuitable to be used for fill include:
i. Unsatisfactory Soils: ASTM D 2487 soil classification groups GC,
SC, ML, MH, CL, CH, OL, OH, and PT, or a combination of these group
symbols.
ii. Expansive clay or carbonaceous soils.
iii. Materials such as coal ash, wood chips, stumps, branches, boughs,
or construction and demolition debris.
iv. Satisfactory soils not maintained within 2 percent of optimum
moisture content at time of compaction.
It is recommendation of this Committee that all project budgets have
a contingency included in anticipation of excavation of unsuitable material.
Users are directed to AIA/MBA Joint Committee Recommended Construction
Practices C-8: “Investigation of Soil and Sub-Surface Conditions”
for related information regarding excavation and D-7: “Unit Prices”
for related information regarding cost control of excavation.
Revised October 2008
Revised May 1996
Revised April 1987
Reviewed February 1986
Revised February 1976
Revised November 1971
Reviewed January 1967
Top of Page | AIA-MBA Home Page
| Organization | Drawings &
Specifications | Bidding | Contracts | Temporary Services
| Bonds, Insurance & Liability
| Safety Responsibilities | Release of Liens
| Procurement Methods & Supplements
| Contact Us |